Project

Total 3건 1 페이지
  • 3
    Paju, Korea
    Location : Paju, Korea
    Client : Korea District Heating Corporation
    Construction Period : Dec2007 ~ Fab2011
    Scope of Work : *Engineering, Procurement and Construction Works for 500MW Combined Cycle Power Plant. *G/T :170MW * 2Units(MHI) *S/T :170MW * 1Unit(MHI) *HRSG :BHI *Heat Output : 420Gacl/h
    Paju, Korea 
    작성자 최고관리자 작성일 08-22 조회 607
  • 2
    Hwaseong, Korea
    Location : Hwaseong, Korea
    Client : Korea District Heating Corporation
    Construction Period : Apr2005 ~ Nov2007
    Scope of Work : *Engineering, Procurement and Construction Works for 500MW Combined Cycle Power Plant. *G/T :170MW * 2Units(MHI) *S/T :165MW * 1Unit(MHI) *HRSG :Doosan *Heat Output : 396.6Gacl/h *Main Cooling Water Pump, Boiler Feed water Pump -14,150t/h*3Units(27m) -HP
    Hwaseong, Korea 
    작성자 최고관리자 작성일 08-22 조회 782
  • 1
    Cogeneration Power Plant
    Location : Incheon, Korea
    Client : Korea National Housing Co.
    Construction Period : Aug2003 ~ Aug2007
    Scope of Work : *Construction Works for Power Plant. *S/T :24MW * 1Unit (Shin Nippon Machinery) *Main Boiler :112T/H * 1Unit(Dong bu Heavy Industries) *HOT :68T/H * 3Units
    Cogeneration Power Plant
    작성자 최고관리자 작성일 08-17 조회 861